Order details
Order details opens when you click any production order card. From top to bottom:
- The order, item, quantity, due date and the sales order lines it covers, with Open in BC links.
- Status chips: status, priority, planned late, Material short, QC hold, Ready to finish.
- A red QC hold banner (with Release hold) or a green Every operation is finished banner (with Change status to Finished).
- Routing: each operation with machine or bay, planned start and end (editable), work time, setup/run/wait/move, started and finished times, output and scrap, and the operator buttons (Start, Pause, Resume, Report output / finish).
- Material & labor: operations done, material consumed, BOM lines done and labor hours, with buttons to Consume materials, Labor and MRP for this order, and the first parts short.
- Footer: Auto-schedule remaining operations, Put on QC hold…, Send back for rework…, Delete production order (only when allowed).
Capacity load
Capacity load shows planned hours against available hours per machine per day, so you can see overloaded bays. Available hours come from the calendars calculated in BC.
Routings
Routings lists the master routings. You can edit:
- Setup, run, wait and move time.
- Send-ahead quantity.
- Concurrent capacities.
- Scrap.
Tick apply to open orders to update the same operation on Firm Planned and Released orders.
A routing must be Certified before orders can use it.