Planning view
The Planning view is where demand becomes work. Released sales orders wait in a queue; you drag them onto the plan, and Raseel creates the production order in Business Central for you.
A Firm Planned order can always go back to the queue; a Released one only until work starts.
Create a production order
- Open Planning.
- Find the sales order in the queue. Use search or filters to narrow the list.
- Drag the order into the plan.
- Choose the status: Firm Planned if you are committing it to the plan, or Released if it is ready for the floor now.
- Raseel creates the production order in Business Central, applies the item's approved routing, and plans its operations.
- The new order appears on the plan and, once released, on the Schedule and Floor views.
Firm Planned or Released?
- Choose Firm Planned when you want to reserve the work and see its effect on capacity, but the floor should not start yet.
- Choose Released when materials and capacity are ready and the floor can begin.
Remove a production order
If plans change, delete the production order from the board. The sales order goes back into the planning queue so you can plan it again later.
- Firm Planned orders can always be removed.
- Released orders can be removed only if nobody has started work or reported output on them. Once work has begun, speak to your supervisor.
Good to know
- An item needs an approved (certified) routing in Business Central before Raseel can plan it. If an order will not plan, see Troubleshooting.
- You never need to open Business Central to create the order; Raseel does that step.